Streetscape Project Update

APRIL 19, 2024

Substantially more sidewalk, curb and asphalt were removed and replaced this past week on both sides of North Main Street and on W. First Street as well. Underground conduit was also installed as the vast majority of above-ground electric lines have been removed. New light pole foundations are being constructed for the decorative light poles. Next week, the contractor will continue with these items.

Smith Paving & Excavating is still confident that the project will be virtually complete by Memorial Day Weekend. The asphalt overlay and paint-striping will likely be completed after Memorial Day Weekend, but it will be really nice to have the other components of the Streetscape finished next month.

The downtown businesses should all be accessible (walking) beginning Saturday, April 20th, so please feel free to patronize local businesses now that the concrete work is getting closer to completion. Mayor and Village Council greatly appreciate the sacrifices and flexibility shown on the part of the downtown business community.

APRIL 12, 2024

Smith Paving has switched over to the east side of N. Main Street and continued removing existing sidewalk on the east and poured a great deal of new sidewalk on the west side of Main Street this past week. Miller Cable has removed traffic light poles, traffic lights, cable/wire, and pole foundations throughout the downtown area. Also, abandoned coal chutes have been mitigated and back-filled under the subgrade for the sidewalk.

Smith Paving plans on pouring concrete next week where they have removed sidewalk and curb, particularly on the east side of North Main Street. They also hope to remove storm infrastructure and additional sidewalk next week. Miller Cable will continue to work behind them, pouring street light pole foundations on both sides of Main Street. Miller Cable plans on installing new street lights within the next two weeks. Once the new lights are energized, the old street lights will be removed and the remaining new sidewalk and light pole foundations will be poured.     

Smith Paving has indicated that they still plan on wrapping most of this project up by Memorial Day Weekend, which would be ideal. Kokosing may perform the asphalt work later in the summer, but the rest of the construction will likely be completed by Memorial Day Weekend, if the spring weather cooperates.

Motorists may park on either side of Main Street where there is no construction prohibiting such parking. Mayor and Council greatly appreciate the sacrifice the merchants and the entire community is making in allowing this construction to continue safely. Thank you all for your patience during this construction.

APRIL 5, 2024

This past week’s weather set the project back a bit, but today the crew was able to get the majority of the concrete poured on the west side and they plan to start the east side of Main Street on Tuesday. Monday the crew will be off, due to the solar eclipse.

Miller Cable was able to remove traffic on signals as most local pedestrians and motorists likely noticed, and the sub-contractor began work on installing underground conduit to power the new decorative lighting. 

Tuesday the contractor plans to start on the east side of N. Main Street. They’ll begin on the south end and work their way north. They are going to remove all of the sidewalk, then pour back the 7′ or so initially against the buildings downtown. This will most likely take place later next week if weather permits. The foreman will touch base with all of the businesses to let them know.

Once again, on behalf of the contractor, Mayor and Council want to thank the entire community for their patience and for using extra caution when walking/driving through the construction area downtown.

MARCH 28, 2024

Smith Paving has made a great deal of progress on the Streetscape Project in just two weeks. They have removed hundreds of feet of existing sidewalk and curb and they have begun to install new curb.

We are pleased that motorists have adjusted well to the new four-way stops at all three intersections, which makes it safer for motorists and pedestrians alike. Numerous local residents have commented that traffic downtown seems calmer overall with the four-way stops.

The contractor plans on removing all traffic lights next week so they can begin installing underground electric lines for the new decorative street lights. The existing streetlight poles and unsightly overhead electric lines will eventually be removed.

This project is a big change for the downtown corridor and Mayor and Council fully understand that, and thus, greatly appreciate the patience and understanding of the entire Fredericktown Community, but particularly that of the merchants. We will continue to work with both Smith Paving and the Ohio Department of Transportation in keeping the community apprised of progress on this project.

MARCH 22, 2024

This past week, Smith Paving worked on removing sidewalk and curb on the west side of N. Main Street. Traffic lights were switched to red-flashing in all four directions. In addition, stop-signs were installed in all four directions at all three intersections as well.

Next week, the contractor plans on continuing work on the west side of Main Street, and they will be filling abandoned underground coal shoots in front of the buildings as well. If weather permits, they hope to begin pouring curb on the west side. They will also be working on coal shoots on the East side in front of some buildings. These abandoned coal shoots must be filled with gravel so they don’t create a sinkhole at any point in the future. In other words, we don’t want to remove downtown sidewalks again in our lifetime, unless absolutely necessary. 

We have had complaints about motorists running stop signs and flashing red lights downtown. Please be advised that the police are patrolling the downtown area for your safety and may indeed issue citations to those motorists that are caught not stopping for the lights and signs. Our goal is to experience absolutely no motor vehicle accidents throughout this project. It is essential to the workers, downtown pedestrians, and other motorists that we keep the construction zone as safe as possible. Thank you for your patience and understanding.

MARCH 19, 2024

TRAFFIC PATTERN CHANGE…

All three intersections on Main Street are now four-way stops.

MARCH 15, 2024

Smith Paving & Excavating will begin removing curb and gutter on the west side of N. Main Street next week. This past week, they focused on surveying and saw-cutting asphalt and concrete. We are happy to see the project get started, so the Streetscape construction will likely be completed sooner than we originally anticipated. Thank you all for your patience.

MARCH 14, 2024

Smith Paving & Excavating began surveying on March 11th and began construction on March 14th.

Two-way traffic will be maintained throughout the project.

Once Smith Paving & Excavating has finished with sidewalks, streetlights, etc., Kokosing Construction will re-pave Main Street, from Mill Street to Sandusky Street.

Smith Paving & Excavating will return later in the year to plant trees and finish cosmetic details.

Goal for the Streetscape project is to minimally impact businesses. However, there will be temporary closures for pouring of concrete, etc.

The Streetscape Project was made possible through an ODOT TAP Grant in 2019 which will cover $1.3 million of the $1.7 million project.